Carruthers Renovation Update

Facilities Management has made great progress working through the demolition portion of the project.  Here are some updates, as of the end of June:

  • 95% done with demolition
  • Roll-back windows for Access Management and Communication Services removed
  • Domestic hot and cold water shut off (6/25-6/26) to rework the plumbing system.  
  • Framing began (6/27)

The Core and Advisory Renovation committees took a site tour of the front area on June 21. As you can see, a lot of work has been done and the space looks totally different!